Mrs Kauffman, Accrington
Drilling of a 150mm finished diameter borehole to a depth of 60m. Installation of permanent pumping equipment and pressure cylinder system.
Drilling of a 150mm finished diameter borehole to a depth of 60m. Installation of permanent pumping equipment and pressure cylinder system.
Borehole drilled to a finished diameter 350mm depth 100m. 21day constant rate test pumping of the borehole using data loggers installed in off site sources also. Permanent pump installed and abstraction licence application.
Borehole finished diameter 300mm to a depth 185m, lined to 130m.
Borehole drilled to finished diameter 450mm depth 125m, associated permanent pumping equipment.
Replacement borehole with a finished diameter 600mm to a depth of 150m. Carry out a constant rate test on the borehole using a 450m3/hr test pump installed on 250mm diameter flanged rising main. Completion of a 28day constant rate test pumping with 24hr monitoring. Supply and installation of permenant pumping equipment with invertor drive starter […]
Abstraction borehole with a finished diameter 610mm, constructed through sand and gravels to the full depth at 1200mm diameter followed by installation of a 610mm diameter stainless steel well screen and gravel pack. Carry out a 28 day constant rate test pumping at a rate of 250m3/hr with 24hr monitoring.
Borehole drilled to a finished diameter of 500mm and to a depth 150m, with permanent pumping equipment and control panel with inverter drive. Abstraction licence application
Liverpool City Centre – Drilling of 6no. boreholes finished diameter 550mm, to depths between 80m and 120m on the streets of the city centre. Extensive test pumping carried out.
Deerplay, Bacup – finished diameter 600mm to a depth of 140m, 28 day constant rate test pumping at a rate of 300m3/hr. Permanent pumping equipment installed.
Borehole drilled to a finished diameter 400mm to a depth of 80m and installation of permanent pumping equipment. One of a series of boreholes on site used to supply the hospital which relies 100% on their borehole supplies.
Borehole with a finished diameter 250mm depth 85m, permanent pumping equipment, abstraction licence application.
2no. boreholes finished diameter 300mm depth 80m, extensive test pumping to the new boreholes and existing boreholes on site. Completion of abstraction licence applications.